The company invoked a force majeure clause after permit delays threatened the 2028 timeline for the AI facility known as Project Jupiter.

Oracle warned the developer of a massive New Mexico AI data center that it may delay contract payments if the project does not come online as planned by 2028, according to a Bloomberg report cited by Morning Brew.
The project, known as Project Jupiter, has faced delays as permits for a natural gas pipeline needed to fuel the facility remain stalled amid local opposition. Oracle, the data center's main tenant, invoked a force majeure clause that shields it from liability for events outside its control, while saying it remains committed to the project.
The warning adds uncertainty to a project that hinges on Oracle's continued payments: roughly $18 billion in debt tied to the project is already trading at 90 cents on the dollar amid concerns about Oracle's debt load, according to a Financial Times report cited by Morning Brew. Oracle's stock fell nearly 3.5% the day the news broke, while shares of developer Blue Owl Capital dropped 3.6%.
Project Jupiter is part of the broader Stargate initiative, a $500 billion effort to build data centers for OpenAI that President Trump has publicly touted alongside OpenAI and Oracle leadership.
From NetWorthy
Every story, one email, 8am daily.
Subscribe at the bottom of this page.
More Economy.
- 01Lawmakers From Both Parties Push To Cap Student Loan Interest Rates
- 02Half of 2025 College Grads Are Underemployed. The Hiring Market Explains Why.
- 03Loudoun County, home of 'Data Center Alley', hits the brakes on new projects
- 04Data Center Construction Costs Jumped 13% This Year As AI Demand Outpaces Supply